Construction updates around the city of Hudson

Projects being worked on as of July 14

Published:

Note: All construction dates are tentative and weather permitting.

Asphalt Program
Crews will begin working on College Street on Monday or Tuesday and the Weston Drive area on Tuesday or Wednesday. The work will consist of milling off the old road and doing cement stabilization. This process will take approximately six weeks to complete, weather permitting. After those areas are completed, the contractor will begin work in the Londonairy Blvd. neighborhood. This work should begin in mid-August and will take six weeks to complete. Finally, work will begin in the Nicholson neighborhood. This too will take six weeks and restoration should be done by mid-October.

Crack Sealing Program
Currently the contractor is working on SR 91 between SR 303 and Terex Road. Streets left to crack seal are:

•Ravenna Street from SR 91 to Stow Road
•Terex Road from SR 91 to SR 303
•Valley View Road from SR 91 to the Corporate line

This work is expected to be completed by the end of July, weather permitting.

Concrete Program
Beginning July 15 through 23, contractors will be repairing sidewalks throughout the City. Sidewalk repairs are determined based on safety and condition of the concrete.

On July 24, we will begin curb repairs to the Northwest corner of the SR 91 and SR 303 intersection.
July 21 through August 1, our contractor will begin work in the First & Main area, replacing certain segments of the tree lawn with brick pavers.

August 18 – 27 crews will install new curbs on SR 91 and Hudson Drive in conjunction with work being done by Hudson Public Power.

Other Construction Projects
Sullivan Road: On July 16, if the weather cooperates, we will be closing Sullivan Road at 5114 to replace an 18-inch crossover pipe. The road will be closed at 8:00 am and reopen 3:30 pm every day. It will take approximately one week to replace the pipe.

SR 303: Karvo is scheduled to mill and pave the two areas on Rt. 303 (westbound side at Hudson Crossings and eastbound side, west of Stow Road) tomorrow at 7:00 pm. They will also fill in driveway ruts adjacent to the drive apron with grindings (458 W. Streetsboro Rd.) at that time. The milling at the catch basin will take place next week.